CASE STUDY 1 — Piping Project in a Paper Mill
The challenge: The client provided initial design + isometrics, but a site inspection revealed major differences that were going to cause execution delays. The solution: Site measurements, building a new AS-BUILT 3D model, redesigning and producing clean isometrics. The result: a smooth, problem-free installation, cost savings and work delivered ahead of schedule.